How gas engines and aeroderivative, industrial and frame turbines compare on efficiency, hot-day output, load steps and N+1 sizing.
Grid queues have moved on-site gas generation into the main power plan for many AI campuses, as bridge power or permanent prime power. The prime mover then sets the unit count, gas supply specification, emissions permit, battery size and how much plant sits idle to deliver N+1.
Four families, from under 3 MW to over 400 MW per unit, behave very differently at 35 °C, at half load and after a load step. Below we compare them on manufacturer ratings, then size a 50 MW IT campus both ways.
Four families and where they fit
Reciprocating engines. High-speed gensets such as Caterpillar's G3520 Fast Response (2.6 MW) and CG260-16 (4.0 to 4.3 MW) and the Jenbacher J620 (3.1 MW). Medium-speed engines: the Jenbacher J920 FleXtra (up to 10.6 MW), Wärtsilä 34SG, 31SG and 50SG (up to 10.8, 12.7 and 18.9 MW) and Everllence 35/44G (formerly MAN, up to 12.9 MW mechanical).
Aeroderivative turbines. Aircraft-engine cores in modular or trailer packages: GE Vernova's LM2500XPRESS and TM2500 (34.5 MW net) and LM6000 (up to 56.9 MW), and Siemens Energy's SGT-A35 (31.8 to 38.1 MW) and SGT-A45 (41 to 44 MW).
Industrial turbines. Heavier machines from oil, gas and CHP duty: Solar Turbines' Titan 130 (16.5 MW) and Titan 250 (23.1 MW), and Siemens Energy's SGT-400 (up to 14.3 MW), SGT-600 (24.5 MW) and SGT-800 (up to 62.5 MW).
Heavy-duty frame turbines. GE Vernova's 7HA.02 and 7HA.03 (384 and 430 MW). One unit approaches the whole load of most campuses, so they suit gigawatt sites.
| Reciprocating engine | Aeroderivative | Industrial turbine | Heavy-duty frame | |
|---|---|---|---|---|
| Unit size (manufacturer rating) | 2.6–18.9 MW | 31.8–56.9 MW | 12.9–62.5 MW | 384–430 MW (60 Hz) |
| Simple-cycle efficiency | 43.0–52.2% | 34.8–41.0% | 33.6–41.1% | 42.6–43.3% |
| Combined-cycle efficiency | Up to 54% (Wärtsilä Flexicycle) | 54.5% gross (SGT-A35 1x1) | Up to 60.6% gross (SGT-800) | 63–64% net (7HA) |
| Start to full load | 10 s to 5 min | About 5–9 min | About 10 min (SGT-800) | 10–21 min (hot start) |
| Hot-day output loss | Under 2% at 45 °C (Wärtsilä) | 5–10% per 10 °C above 15 °C | 5–10% per 10 °C above 15 °C | 5–10% per 10 °C above 15 °C |
| Fuel gas pressure | About 6 bar (Wärtsilä) | Nearly 50 bar or more | Model-specific | Model-specific |
| Minimum stable load | About 10% per unit | About 40–50% | Model-specific | Model-specific |
| Typical data-centre role | Modular prime and bridge power | Fast bridge power, larger prime plants | CHP and combined-cycle campuses | Gigawatt campuses |
Manufacturer ratings at each OEM's reference conditions; they vary by configuration and frequency. Turbine derating and minimum loads come from Wärtsilä's comparison, so check them against turbine OEM curves.
Efficiency at full and part load
The Wärtsilä 20V34SG has a heat rate of 7,363 kJ/kWh at 50 Hz; the LM2500XPRESS+G4 is 9,146 kJ/kWh net. The turbine burns 24% more gas per MWh (9,146 ÷ 7,363 = 1.24), or about 1.0 million GJ more over a year at 65 MW (569,400 MWh × 1.783 GJ/MWh). The OEMs quote at 25 °C and 15 °C respectively, so compare site-rated heat rates in the tender.
Combined cycle narrows the gap (54.5% gross for an SGT-A35 1x1 plant, up to 54% for Wärtsilä engines with steam bottoming) but adds a steam cycle and slower starts.
Part load separates the families. In Wärtsilä's part-load comparison, a single aeroderivative at 50% load falls to nearly 30% efficiency against over 40% for an engine, and the turbine's emissions-compliant minimum is about 40% to 50% of rating against 10% per engine. Engine plants follow load by stopping units, which matters during phased fit-out.
Starting, load steps and AI training swings
The G3520 Fast Response accepts load 10 seconds from a cold start and takes a 100% block load (ISO 8528-5 class G2). INNIO's data-centre J620 sheet gives full power 45 seconds after the start command, pre-heated, and a single 100% load step. Wärtsilä medium-speed engines reach full load in under 2 minutes on a fast start; aeroderivatives take about 5 to 9 minutes.
A CIMAC position paper notes markedly lower load acceptance in lean-burn, high-BMEP gas engines and places most in ISO 8528-5 class G4, agreed case by case. Wärtsilä credits engines with ramp rates above 100% of load per minute against 50% for aeroderivatives.
Researchers from Microsoft, OpenAI and NVIDIA report that synchronised training can swing site demand by tens to hundreds of MW, mostly at 0.2 to 3 Hz, overlapping generator and grid oscillation modes. A grid-forming battery should absorb the fast component while gensets follow the envelope. Wärtsilä Energy Storage told Energy-Storage.news in June 2026 that islanded AI campuses are close to unworkable without storage, and starts sizing at the power of the swing with 2 hours of duration. Smaller engine units leave the battery less to cover after a trip.
Heat, altitude, gas pressure and water
Turbines are rated at 15 °C (ISO 3977), and Wärtsilä's rule of thumb is a 5% to 10% output loss and about 1% efficiency loss for every 10 °C above that. Siemens Energy's SGT-A45 data agree: 44.0 MW at 15 °C becomes 39.6 MW at 30 °C (60 Hz), a 10% loss. Inlet cooling or water injection recovers output at the cost of water; altitude cuts it further.
Wärtsilä states full engine power from −45 °C to 50 °C and above 1,200 m, but the 2019 J620 data-centre sheet lists −37 °C to 37 °C, so specify engines for the climate.
Wärtsilä engines run at full power on 6 bar of gas, against nearly 50 bar for aeroderivatives; some aeroderivatives need above 900 psig (about 60 bar). Below that, a fuel gas compressor is needed, as in each LM2500XPRESS package ordered by Crusoe, adding parasitic load and its own redundancy requirement.
Wärtsilä puts engine plant water use below 5 litres per hour against nearly 12,000 litres per hour for an aeroderivative using water for NOx control and cooling. Turbines win on density: Siemens Energy cites 175 MW from four SGT-A45 units on about one hectare, while one 18V50SG genset weighs 377 tonnes dry.
Emissions, maintenance and redundancy
Raw NOx favours dry low-emission turbines (15 ppm for the LM2500XPRESS, 9 ppmvd for the SGT-600) over engines (90 ppm for the 50SG), but data-centre plants of both kinds, including Crusoe's turbines and Everllence's 480 MW engine plant, use selective catalytic reduction (SCR), so budget for reagent and catalyst.
Jenbacher distributor Clarke Energy lists engine servicing every 1,000 to 2,000 hours and a major overhaul at 60,000 or 80,000 hours; Siemens Energy schedules SGT-A45 maintenance every 25,000 hours. Engine fleets see many short outages, turbine fleets fewer, longer ones.
N+1 on many small units costs one small unit; on two or three large units it adds 33% to 50% of capacity. A unit in service turns N+1 into N, so decide whether service windows need N+2.
Market context in 2026: backlogs and lead times
GE Vernova's gas turbine backlog plus slot reservations reached 116 GW at the end of Q2 2026, up from 100 GW a quarter earlier, with Q2 orders for 52 heavy-duty and 61 aeroderivative units (Turbomachinery, July 2026). Siemens Energy's backlog was 69 GW at June 2026, with group lead times of three years or more, and it described itself as booked out to fiscal 2028. Mitsubishi Heavy Industries' large-frame backlog rose to 35 GW, with new orders scheduled for delivery in 2028 to 2030 (August 2026).
Engines have taken gigawatt-scale data-centre orders, including 2.3 GW for INNIO and 2 GW for Caterpillar (POWER, March 2026), but they queue too: Wärtsilä booked 1.2 GW of data-centre orders in Q2 2026 and reported rising delivery times.
Worked example: 50 MW of IT on N+1 prime power
Assumptions: 50 Hz, 35 °C design ambient, plant auxiliaries excluded. Engines: Wärtsilä 20V34SG at 9,795 kW (manufacturer rating at 25 °C), derated 2% (Wärtsilä reports under 2% at 45 °C). Turbines: LM2500XPRESS+G4 at 34.5 MW net (ISO), derated 15%, the midpoint of 5% to 10% per 10 °C over the 20 °C above ISO.
- 1.Facility load: 50 MW × 1.3 PUE = 65 MW.
- 2.Engines: 9.795 × 0.98 = 9.60 MW each. 65 ÷ 9.60 = 6.8, so N = 7 and N+1 = 8 units, 78.4 MW installed. Firm capacity with one unit out: 7 × 9.60 = 67.2 MW.
- 3.Turbines: 34.5 × 0.85 = 29.3 MW each. 65 ÷ 29.3 = 2.2, so N = 3 and N+1 = 4 units, 138 MW installed. Firm capacity: 3 × 29.3 = 87.9 MW.
- 4.Unit trip: an engine trip removes 9.6 MW (15% of load) and lifts survivors from 85% to 97% of rating; a turbine trip removes 29.3 MW (45%) and lifts survivors from about 55% to 74%.
- 5.Half load (32.5 MW) with spinning N+1: five engines run at 68% each (32.5 ÷ 48.0); three turbines run at 37% each (32.5 ÷ 87.9), below the 40% to 50% minimum, so the turbine plant drops to two units and loses its spinning reserve.
- 6.Battery: for an illustrative swing from 20% to 80% of IT load, 0.6 × 50 = 30 MW, so start at 30 MW and 60 MWh. That covers an engine trip with margin; a turbine trip uses almost all of it.
- 7.Headroom: turbine firm capacity carries 67.6 MW of IT (87.9 ÷ 1.3), or 58.9 MW at 45 °C with a 26% derate (3 × 34.5 × 0.74 ÷ 1.3); the engines need a ninth unit above 51.7 MW of IT (67.2 ÷ 1.3).
Result: engines meet N+1 with 1.21 MW installed per MW of load against 2.12 for turbines, a 15% single contingency and stable part load. Turbines need half the units and suit a campus that will grow into the spare capacity.
What this means for your programme
- Fix design ambient and altitude first, get site-rated output and heat rate from every OEM, and size N+1 on derated figures.
- Ask each supplier for its load step table: largest step from each base load, frequency dip, recovery time and the ISO 8528-5 class offered.
- Specify the battery with the generation, rated for the larger of the training swing and the largest unit trip; Wärtsilä cites about 18 months of battery lead time.
- Confirm year-round gas pressure at the site boundary; if it falls below the turbine requirement, budget a compressor train with its own N+1.
- Model fuel and emissions at each fit-out phase's part load, on common reference conditions.
- Count planned outages per year and decide between N+1 and N+2.
- Get firm delivery dates, slot reservation terms and factory test dates in writing before financial close. Nodus secures gas engine gensets, gas turbines and bridge-to-grid packages for data-centre programmes that cannot wait for a grid connection.
Sources
- Wärtsilä: Technology comparison, derating due to ambient temperature
- Wärtsilä: Wärtsilä 34SG gas engine performance data
- INNIO Jenbacher: Data centre application sheet (J620)
- Caterpillar: Cat G3520 Fast Response natural gas generator set
- GE Vernova: LM2500XPRESS aeroderivative gas turbine
- Siemens Energy: SGT-A45 TR data sheet
- Solar Turbines: Titan 250 generator set
- GE Vernova: Second quarter 2026 financial results
- Utility Dive: Siemens gas turbine backlog nears 70 GW as company expands manufacturing
- arXiv (Microsoft, OpenAI, NVIDIA): Power stabilization for AI training datacenters
General information only, not investment, financial or technical advice. Figures are drawn from the sources listed and may change; illustrative assumptions are labelled as such.